Development timeline

This page provides a timeline of key events in the development of Tonstad DataPark, from the public announcement of the zoning process in 2018, through municipal zoning decisions, the facility licence granted by the Norwegian Water Resources and Energy Directorate (NVE), and GreenScale’s acquisition of Tonstad Data Park in 2025. The timeline highlights major milestones including zoning decisions, regulatory approvals, community town hall meetings, the start of site works in 2026, and anticipated development phases leading toward the first operational building and full campus completion.
October2018

Zoning process announced

The commencement of the detailed zoning process for the Ertsmyra Næringsområde is announced. The announcement refers to plans to establish a data centre within the planning area.
March2020

Industrial zoning approved

Sirdal municipality zones the land for industrial use.
August2020

Facility licence application

Tonstad DataPark applies for a facility licence.
February2021

Landowner consultation

NVE (Norges vassdrags- og energidirektorat) sends formal notice to potentially affected landowners regarding the facility license for Tonstad DataPark.
April2021

Consultation closes

The NVE consultation period closes.
June2021

Facility licence granted

NVE grants the facility licence for Tonstad DataPark.
July2024

Zoning update announced

The municipality announces change in zoning with mention of data centre in the zoning plan.
October 2024

Zoning amendment submitted

Application to amend the zoning to add "data centre” (due to a national legislative change).
June 2025

Acquisition plans announced

GreenScale announces its intention to acquire Tonstad DataPark.
September 2025

GreenScale acquires Tonstad DataPark

GreenScale completes the acquisition of Tonstad DataPark.
October2025

Community conversations

GreenScale holds its first town hall meetings with residents and local and regional businesses.
November 2025

Grid reservation allocated

Statnett allocates a 300 MVA grid reservation.
December2025

Josdal town hall

GreenScale meets with Josdal residents and cabin owners.
February2026

Site works begin

Site clearing work commences.
Late2026Expected

Frame permit submission

Anticipated submission of the frame permit application.
Late2026Expected

Site levelling

Anticipated start of site levelling.
2028Expected

First building operational

The first building is expected to become operational.
2030Expected

Full campus operational

All buildings are operational.